Leading the integration layer of an airline's move from in-house flight movement systems to CAE Movement Manager: 13 integrations, a new message-broker architecture, two onsite UAT cycles, and a cutover that happens while the airline keeps flying.

Challenge

The flight-ops system of record feeds everything downstream: crew tools, the passenger system, flight planning, maintenance, fuel, ACARS. Replacing it is open-heart surgery on a live airline. A full mesh of interdependent integrations had to be rebuilt against the new platform, validated with the business, and cut over with no interruption to daily operations.

Approach

  • Stood up an in-house ActiveMQ broker as the hub for every outbound message to the new platform and migrated the MuleSoft integration apps onto it; refactored ACARS forwarding from RabbitMQ to the new broker.
  • Built or hardened each integration by system: charter platform (multi-leg, IROPS, diversions, upsert, closed-on-OOOI), Navitaire passenger and bag counts, NavBlue flight-schedule sync over SOAP with diversion handling, Kronos flight messages, SSIM to AMDM, SlickOR feed, Ops Web remarks templates, and the Merlot crew-system CSV path.
  • Ran two onsite cycles with the vendor (a two-week UAT with the business in the room, then a design workshop) and a full mock run that produced the rollout plan, configuration naming conventions, and deployment guidelines.
  • Audited every passenger-sync integration for UTC/local date-crossover risk and drove datetime-anchored fixes across sync filters and validation logic.
  • Inventoried vendor endpoint, DNS, and external-network dependencies for release readiness; reconciled legacy UI roles to the new auth model one-to-one.
  • Owned the risk register: roughly 20 dependencies across cloud engineering, SRE, DevOps, InfoSec, and the vendor, each driven to closure before cutover.
  • Authored developer-ready tickets for every re-pointed integration: flight status sync, OOOI events, passenger counts, weight and balance, and crew-facing flight lookup.

Outcome

  • 13 systems integrated against the new system of record with operations running throughout.
  • Six vendor escalations resolved: an unannounced platform upgrade that dropped all inbound traffic, ACARS queue consumption, a diversion-event bug, missing message triggers, web-services authentication, and a SOAP interface enhancement.
  • Date-crossover risk affecting roughly 94 flight legs a day identified and fixed at the sync-filter level before it reached production.
  • Risk register empty for the four sprints before cutover; the legacy crew-view system reduced to view-only with the new platform as its flight-data source.

Systems involved

  • CAE Movement Manager
  • MuleSoft / CloudHub 2.0
  • ActiveMQ
  • Navitaire
  • NavBlue NFP
  • ACARS
  • Kronos
  • Merlot
  • AirlineChoice
  • SlickOR
  • CAE AMDM

Milestones

  1. Nov 2026CAE Movement Manager go-liveUpcoming
  2. Jun 2026Final CAE UAT and full mock cutover run
  3. Dec 2025CAE onsite workshop and new broker architecture
  4. Oct 2025First CAE UAT cycle with the business onsite
  5. Aug – Dec 2025CAE Movement Manager integration build